Archive for the ‘PMP’ Category

PMP Brain Dump Cheat Sheet

Sunday, May 24th, 2009

While I was preparing for my PMP, I was shown a fantastic way to structure a brain dump sheet that I thought I’d share.  When you take your PMP exam, you’re given 6 sheets of paper, 2 pencils, and a calculator.  Pretty much every PMP training program andbook out there will tell you that the first thing you should do when you sit down is do a brain dump.  

A brain dump is taking everything you’ve crammed into your head over the last several days or week and dumping out onto one of the sheets of paper so that you don’t forget it when trying to take the test.  I developed my brain dump cheat sheet early on in my preparation, and I practiced it every day for 3 weeks prior to taking my exam.  I would just begin my study time by performing a brain dump in a spiral notebook.  I’d go as far as I could remember, and then I’d go back and re-read the previous day’s dump to fill in the gaps.  Then I’d do it again the next day.  The point was not to remember everything right away, but to remember as much as I could so that I could get as far into my dump as possible when sitting for the actual test itself.

So what went into my brain dump?  For starters, the most complex part of the test, for me, was recalling all of the different formulas.  So here’s what I did.  Starting with a blank sheet, I’d draw two lines, giving me three columns.  I would then build a grid, like an Excel worksheet.  In the upper right hand cell, I’d write “cost”.  In the cell immediately to the left I’d write “schedule”.  These acted as headers for the first few formulas I was going place in the grid. Now comes the fun part, filling in the gaps.  The first 4 rows are dedicated to the Schedule and Cost headers.  The remaining rows are simple, three part break downs of the calculations needed (meaning that the schedule and cost headers do not apply).

  Schedule Cost
Variance EV-PV EV-AC
Index EV/PV EV/AC
  SPI CPI
EAC (=) BAC /CPI
ETC EAC -AC
VAC BAC -EAC
TPA CP-TP /Y%+TC
PV FV /(1+r)n
FV PV *(1+r)n

 

This simple little worksheet made it so that I did have to try to remember the formulas while I in the middle of trying to solve the particular question.  So if a question came up and said something to the effect of “EAC=10 BAC=15.  What is the VAC?”, I’d just look up the formula on my sheet and do the math.  Now, the questions weren’t quite that striaght forward in all cases, in fact they were more likely to give me the CPI and the BAC numbers and have me calculate the EAC in order to find the answer for VAC, or something to that effect.

You can also expand the column idea to include the 5 process groups (as the column headers), the 9 knowledge areas (as the far left hand row headers) and then fill in the gaps:

  Initiation Planning Executing Monitor & Control Closing
Communication   Com Plan Info Dist Perf Reporting
Mgmt Stakeholders 
 
Cost   Cost Est
Cost budget 
  Cost control  
H/R   H/R Plan Acquire Proj team
Dev proj team 
Mg proj team  
Integration Project charter
Prelim Scope statement 
PM Plan Dir & Mg proj exe M&C Work
Integrate Change control 
Close
Procurement   Purchases
Contracting 
Req seller responses
Select seller 
Contract admin Contract closure
Quality   Quality plan Proj quality assurance QC  
Risk   Risk Mgmt
Risk ID
Qual Risk Analysis
Risk response 
  Risk monitoring  
Scope   Scope plan
Scope Def
WBS 
  Scope verify
Scope control 
 
Time   Activity Def
Sequence
Resource Est.
Duration Est.
Schedule Dev 
  Schedule control  

You gotta love the grid for breaking down complex information into small, bite-sized pieces!  Now, there are gaps in the 5×9, i.e. there’s no “implementation” item for the “time” knowledge area, so know all of the key areas and fill the blanks with X’s and you’ll be OK.

He’s Certifiable Ya’ll!!!

Monday, October 15th, 2007

Well, after 6 months of intense training and testing, I finally completed my Master’s Certificate in Applied Project Management from Villa Nova University. This means that I now have all of the college credits necessary to go for my PMP, which I should have completed by November, assuming all of my experience is accept by PMI.

Regardless, it’s good to have this done. Now, no matter what I do or where I go I’ll always be able to put “Masters Certificate in Applied Project Management” on my resume, and that’s gotta count for something.